Sizes, parking, and the deed restriction
Those limits are on the city’s Learn the Rules page, which also says a homeowner may build both an ADU and a junior ADU, while a multi-unit property may have one or two ADUs, depending on the project, and may not have a junior ADU. That is what the city page says today. Starting January 1, 2027, AB 956 (Quirk-Silva), Chapter 791, Statutes of 2026 requires cities to ministerially approve two detached, new-construction ADUs with no more than 4-foot side and rear setbacks on a lot with a proposed or existing single-family home. A city may still cap each at 800 square feet of livable space and apply the height limits in Government Code section 66321(b)(4). The city does not have to ministerially approve a junior ADU on a lot where those two detached units were built. Newport's page may not show the new count until the city updates it. Local ordinances have to follow the state rule on January 1, 2027. Confirm with the city. See the 2026 law update. In single-family and multifamily zones the city describes ADUs as ranging from efficiency units up to 1,000 square feet. Internal ADUs and multi-unit conversions have no square-footage cap but are generally stuck inside the existing building envelope. Junior ADUs stop at 500 square feet.
A legally built garage, barn, or similar structure can be converted. A junior ADU can come out of an attached garage, not a detached one. If you demolish a garage and rebuild, the new ADU can reuse that footprint when it matches the old size and height. Demolition of a detached garage can be processed with the ADU permits.
The city does not require the owner to live on the property for an ADU. A junior ADU does, and that duty is recorded. The permit page says the recorded deed restriction also states that the ADU will not be sold off separately and will not be used as a short-term rental.
Parking on the rules page: junior ADUs and internal ADUs do not add a new space. Attached and detached ADUs do, and it may be tandem in the driveway, unless the lot is within a half-mile walk of transit, in an architecturally or historically significant district, in an on-street permit district that does not give a permit to the ADU occupant, within a block of car-share, or outside the Coastal Zone and built with a new building. Replacing uncovered parking is not how an ADU is supposed to find its space. Covered parking that you demolish or convert does not have to be replaced, except for a junior ADU or a Coastal Zone project. Check the current guidebook before you rely on an exception. The permit page’s parking list is written slightly differently and adds “part of a new single-family or multi-unit development” as a case where a new ADU does not need extra parking.
Coastal Zone, Safe ADU, and Edison
The permit page points homeowners to the city’s address search tool, which reports whether the parcel is in the Coastal Zone and who the utility providers are. A coastal lot may need a coastal development permit before plan check, and that permit can require a hearing. The city’s certified local coastal program is the reason. The Community Development coastal development permit instructions (revised October 3, 2023) say a permit is required for development in the coastal zone unless it is exempt or excluded, and they list the findings the review authority has to make. Since October 10, 2025, Government Code section 66329 says the city must approve or deny a completed ADU coastal permit within 60 days and is not required to hold a public hearing. The city page still mentions a possible hearing. Ask the counter which instruction it is using. The statewide walk-through is the coastal zone ADU permit guide.
Safe ADU is the city’s legalization path for an unpermitted unit. Any ADU built before 2020 can qualify if health and safety problems are fixed and the unit meets the current building code. It does not have to meet current zoning, the California Green Building Standards Code, or the California Energy Code. Coastal Zone units still cannot harm public views, public access, habitat, or wetlands. Starting January 1, 2025, AB 2533 is why the city posts a substandard-housing checklist for units built before January 1, 2020. The city’s suggested first call is to Planning without giving your address, so you can hear the general rules before you open a case. Prove the pre-2020 date with utility bills, tax records, a dated rental agreement, contractor bills, photos, or affidavits. The city makes the final call.
Before the final permit, Southern California Edison has to sign off if the ADU is near overhead lines or an easement. The rules page points to an SCE order for that step.
Fees and clocks the city actually printed
Plan check and a building permit are both required, submitted together at the Permit Center. Plan-check fees are due at submittal and, on the permit page, run from $850 to $1,700, based on valuation for a conversion and on floor area for new construction. Building-permit fees are due at issuance and run from $850 to $2,100 on the same basis. School-district fees apply over 500 square feet. Traffic fairshare and transportation-corridor fees apply over 750 square feet. Those are the city's published fees, not a statewide price. Starting January 1, 2027, SB 1117 (Cervantes), Chapter 809, Statutes of 2026 still bars an impact fee on an ADU of 750 square feet of interior livable space or less. On a lot with up to two ADUs, an impact fee on a larger ADU is charged in proportion to the main home and only on the square feet above 750. A lot with more than two ADUs keeps today's proportional rule on the whole unit. The statute applies to charter cities. It does not set Newport's dollar amount. Ask the city for the current fee sheet. See the 2026 law update. Utility and sanitation charges vary. The city says it does not control school and water fees. Separate water and sewer connections are not required, but Public Works or Building may require a larger service or meter.
The permit page says the city aims to return comments in 10 to 20 days, that most projects take two or three rounds, and that the permitting phase is typically 1 to 6 months. The rules page’s full timeline, which it presents as typical rather than guaranteed, is 12 to 18 months for most projects and 24 months or more for some: about 1 to 3 months to assemble the team, 1 to 6 months to draw and submit, 1 to 6 months in review, and 6 to 12 months building. Those are the city’s published ranges, not a promise for your lot.
None of those figures is a construction-contract price. For the contract, our cost guide is a planning estimate only. Compare the coastal path here with Huntington Beach only after you have checked which coastal permit each city actually issues.
Sources
Reviewed October 22, 2026:
- Newport Beach ADU, Learn the Rules — zones, size caps, 30-day rental minimum, owner-occupancy split, timeline.
- Newport Beach ADU, Permit — plan-check and building-permit fee ranges, deed restriction, 10-to-20-day comments.
- Safe ADU — pre-2020 units, building-code legalization, AB 2533 checklist.
- City of Newport Beach, Coastal Development Permit instructions (rev. October 3, 2023).
Share a few details and we will route your request with city page attribution.